Package of 9 transmission lines and substations

Huánuco, San Martín, Cusco, Cajamarca, Piura, Lambayeque y Ayacucho


Factory inspection, detailed engineering review, civil works supervision, electromechanical assembly and more.

Project management. Factory inspection, detailed engineering review, supervision of civil works and electromechanical assembly, and liquidation of work and project, of the following transmission lines and associated substations:

    • Tarapoto – Bellavista 138 kV, 80 km.
    • Tarapoto – Moyobamba 138 kV, 97 km.
    • Aucayacu – Tocache 138 kV, 109 km.
    • Quillabamba – Chahuares 60 kV, 34 km.
    • Cajamarca – Cajabamba 60 kV, 80 km.
    • Ayacucho – Cangallo 60 kV, 60 km. Piura – La Unión – Sechura – Parachique 60 kV, 68 km.
    • Gallito Ciego – Cajamarca (2nd group) 60 kV, 95 km.
    • Chiclayo – Pomalca – Tumán – Cayaltí 60 kV, 40 km.
    • Location: Huánuco, San Martín, Cusco, Cajamarca, Piura, Lambayeque and Ayacucho; Peru.