Expansion and Modernization of the Port of Callao

Callao


Review of the master plan, elaboration of the basic engineering and detailed engineering of the first stage of expansion of the main maritime port of Peru. Container wharf 400 m long. Wharf for grains, 300 m long.

  • Dock for Post Panamax ships.
  • Depth 14m.
  • Dredging of 3.4 Mm3 and filling of 1.6 Mm3.
  • West protection for the container yard (215 m).
  • Silo with storage capacity for 50,000 t.
  • Administrative building, container loading station, maintenance workshop. 2 Gantry Cranes; 5 gantry cranes on rubber wheels, various special forklifts, etc.
  • 2 grain unloaders of 400 t/h.
  • Estimated investment of US $200 million.